Gurus,
I am facing source determination issue for purchase requisition generated after MRP run.
My understanding is Validity period for source list always refers to the requirements date for source determination using planning run. I have 2 vendors which are active during different period. 1st one is active from 03/08/2015 to 08/23/2015 whereas 2nd one is active from 08/24/2015 to 12/31/9999 as below.
What i am expecting is any requirement date falls between 03/08/2015 to 08/23/2015, it should go to vendor # 14138 whereas any requirement data on and after 8/24/2015 should go to vendor # 15251 .
After running MRP, my requirement of 6/17/2015 should go to vendor # 14138 as it's valid during that period but after planning it's going to vendor # 15251. See below.. and that's my issue.
Any help or suggestion ?
Regards,
Ravi.